STATUS ON THE 30TH OF OCTOBER, 2020
Unfortunately the fire gate was delayed in production – and this together with other factors delayed
the hand-over procedure. This was finally carried out on the 28th of October, 2020 and all relevant documentation was uploaded to the authorities the day after. Following a frequent, smooth and constructive dialog during the entire project period we are pleased to confirm that our Municipal Fredericia Kommune issued The Certificate of Release to Service on October 30, 2020.
Enclosed pictures will together with previous pictures complete the journey of the project from idea to reality. Have a look at the enclosed draft presenting the original idea dated 30.07.2019.
The Light Sign on top of the facade of the new building as it looks from the estimated 100.000 vehicles daily passing by on the adjacent motorway. The first trailers arriving for handling. Pictures inside the new storage and handling facility and the gravel area and new fence/entrance.
We are looking forward to continue the pleasant co-operation with all of you.
Click on the picture
STATUS ON THE 17TH OF SEPTEMBER, 2020
It is time for an update now the summer period has passed.
The outside terminal areas are now as close to finished as can be. Like the new building including the concrete floor, the roof and EL-work. The passage between the new and the existing building has been established – here the fire gate remains to be installed as well as a few loading gates and other minor details. On the 11th construction meeting earlier this week it was therefore agreed to aim towards carrying out the handling over procedure on Wednesday the 7th of October, 2020.
We are looking forward to continue the pleasant co-operation with our many clients and thank you very much for your understanding for any inconveniences the building period might have caused.
The enclosed pictures illustrate the development – also that the earth pile now present itself with a new fresh green look.
Click on the picture
STATUS ON THE 19TH OF JULY, 2020
From the project start in the end of March the time has passed by excavation and removal of appr. 15000 cbm soil most of which has been deposited internally in a nice pile adjacent to Taulov Combiterminal. Further more the handling of external deliveries and depositing of appr. 11000 m3 of Sand and appr. 4000 m3 of Gravel and Cruched Concrete.
Please have a look on the pictures to see the development.
In addition to this the majority of the paving has been finished.
This also goes for the foundation of the building, the steelconstruction, the placing of the concrete facade elements and the roof.
Please have a look on the pictures to see the development.
Click on the picture
In addition to this the majority of the paving has been finished.
This also goes for the foundation of the building, the steelconstruction, the placing of the concrete facade elements and the roof.
Please have a look on the pictures to see the development.
Click on the picture
WAREHOUSING JUNE 2020
We are pleased to inform that the extention of our facilities at Europavej 40 are progressing according to schedule. It concerns our 27891 squaremeter site centrally located in the strategic transport corridor adjacent to Taulov Combiterminal.
The extention involves the erection of a 10 meter high storagefacility, which will increase our storage capacity for ordinary goods significantly and also with its fine transitfacilities optimize our trailer handling.
The capacity for storing Dangerous Goods in the 2 existing storage buildings will furthermore increase as the existing transit area together with ordinary goods will be moved to the new facility.
The extension will also give us new possibilities to offer outside storage by the fact that around 10000 squaremeters will be covered out of which appr. 1/3 with Uni-lock stones for heavy traffic and the balance as gravel area for other kinds of storage.
You are very welcome to visit our website click WAREHOUSING and NEWS to see the development.
Bendix Transport Danmark A/S
Jernholmen 39
DK-2650 Hvidovre
Telefon 36 772244
Telefax 36 771502
cph@bendixtransport.dk
Reg.No. 18 23 61 33
Bendix Transport Danmark A/S
Europavej 40, Taulov
DK-7000 Fredericia
Telefon 75 564444
Telefax 75 564400
frc@bendixtransport.dk
Reg.No. 18 23 61 33
To support the environment we ask you kindly to receive your invoice as PDF via E-mail. Please send your Invoice E-Mail-address to invoice@bendixtransport.dk
UK-Invoice to us also to be sent to
invoice@bendixtransport.dk
Thank you in advance.
To all of you from all of us the very best wishes for a Merry Christmas and a Happy and Peaceful New Year.
And not only at Christmas but throughout the year the the joy that we give to others is joy that comes back to ourselves.